Which NERC CIP changes apply to your entity and when
Thirteen CIP standards are enforceable in the United States as of 17 October 2026. The two newest versions are CIP-003-9, which became enforceable on 1 April 2026 and adds vendor electronic remote access controls for low impact BES Cyber Systems, and CIP-012-2, which became enforceable on 1 July 2026 and adds protection of the availability of Real-time data between Control Centers. The next dated changes fall on 1 July 2028 (the virtualization set and the revised Control Center definition), 1 October 2028 (the first internal network security monitoring obligations and the CIP-014 revision) and 1 October 2029 (the CIP-015-2 extension and the CIP-003-11 low impact changes). Each date changes what you must have in place, so a planning calendar should start from the version that applies to each system today rather than from the newest standard number. Which of these changes reach you depends on two inputs: the impact rating your entity assigns under CIP-002-5.1a and the asset types you own or operate. A high impact Control Center operator will feel the 2028 virtualization and monitoring dates across most of its program, while an entity whose assets hold only low impact BES Cyber Systems will mainly track the CIP-003 changes. Before you schedule any work, confirm your current categorization in writing, list which Applicable Systems it produces, and map each enforceable version and each later version to those systems. Ask your Regional Entity or your CIP Senior Manager to confirm any rating that sits near a bright line. The organization owns its compliance. A Regional Entity or NERC monitors it, and no certification body issues a CIP certificate. An implementation partner can prepare systems, documentation and evidence for the 2028 and 2029 changes, but the CIP Senior Manager remains accountable for which version applies, when each change takes effect and whether the entity is ready on each date. Confirm the effective dates against the NERC CIP standards page and the implementation plans for each standard before you commit budget, because those sources govern and this timeline reflects them only as of October 2026.
The dated sequence of NERC CIP changes from 2026 to 2029
This sequence shows which CIP changes are already enforceable, which revisions take effect in 2028 and 2029, and which current versions retire on fixed dates. Each step gives a compliance lead a dated output to produce before the next change lands.
Confirm the 1 April 2026 low impact vendor remote access change
On 1 April 2026, CIP-003-9 became enforceable and added vendor electronic remote access controls for low impact BES Cyber Systems. The CIP Senior Manager or delegate should confirm which low impact assets have vendor remote access, then update the cyber security plan and record the vendor access method and approval for each. The step is done when the plan revision and the vendor access inventory are both dated and approved.
Update Real-time data availability controls by 1 July 2026
On 1 July 2026, CIP-012-2 became enforceable and added protection of the availability of Real-time data sent between Control Centers, on top of the existing protections for confidentiality and integrity. Teams should map the communication links that carry Real-time Assessment and Real-time monitoring data, then document how loss of availability is detected and handled. The output is a current data flow inventory and a dated record of the availability controls on each link.
Track the 26 May 2026 virtualization order
FERC Order No. 919 took effect on 26 May 2026 and approved 11 revised virtualization standards, along with new and revised NERC Glossary definitions. Adoption is not required, but the order changes the language a compliance program will be measured against in 2028. The compliance lead should record the approved standard versions and glossary terms in the program's standards register, and note which of the 11 revised standards apply to the entity's systems.
Plan the 1 July 2028 virtualization and Control Center changes
On 1 July 2028, the virtualization set (CIP-002-7 through CIP-013-3 as listed in Order No. 919) and CIP-002-8 with its revised Control Center definition take effect. Early adoption is available after notifying the Regional Entity at 6, 12 or 18 months after the order's effective date. The entity should decide on early adoption, reassess Control Center classification against the revised definition, and record the gap list for each revised standard. The output is a signed transition plan with named owners.
Schedule retirement of the 30 June 2028 standards
NERC lists 30 June 2028 as the inactive date for CIP-002-5.1a, CIP-003-9, CIP-004-7, CIP-005-7, CIP-006-6, CIP-007-6, CIP-008-6, CIP-009-6, CIP-010-4, CIP-011-3 and CIP-013-2. Evidence collection and procedures tied to these versions should be closed out before that date, with the successor versions in place. The compliance lead should confirm the cut-over date in the NERC standards listing and keep a dated record of the final version in use.
Prepare for CIP-015-1 and CIP-014-4 on 1 October 2028
On 1 October 2028, CIP-015-1 begins internal network security monitoring for high and medium impact systems at Control Centers and backup Control Centers, and CIP-014-4 takes effect with its refined physical security risk assessment. Other medium impact systems with External Routable Connectivity follow within 24 calendar months under CIP-015-1. Teams should confirm monitoring coverage design and update the CIP-014 risk assessment method. The output is a monitoring architecture document and a revised CIP-014 risk assessment ready for review.
Retire CIP-014-3 on 30 September 2028
NERC lists 30 September 2028 as the inactive date for CIP-014-3, which CIP-014-4 retires. The compliance lead should confirm that the risk assessment, physical security plan and third-party review cycle have moved to the CIP-014-4 requirements before that date. Records should show which version governed each assessment, so that the change in method is visible to auditors.
Apply CIP-003-11 low impact changes from 1 July 2029
On 1 July 2029, CIP-003-11 takes effect and adds remote user authentication, protection of authentication information in transit and malicious communication detection for low impact assets. Entities with low impact assets should assess their remote access paths against these three additions and update the cyber security plan. The output is a dated plan revision and test evidence showing the new controls operate on each in-scope asset.
Extend monitoring to EACMS and PACS by 1 October 2029
CIP-015-2, approved by FERC on 10 August 2026, extends internal network security monitoring to associated EACMS and PACS from 1 October 2029, offset 12 months from the CIP-015-1 dates, and retires CIP-015-1. Teams should confirm which EACMS and PACS sit inside the relevant Electronic Security Perimeters and extend the monitoring design to them. The step is complete when the monitoring inventory covers those systems and the CIP-015-1 records are archived under the retirement.
What each change requires from high, medium and low impact entities
The virtualization revisions approved in Order No. 919 update the perimeter-based language in the CIP standards and add terms for virtualization infrastructure and virtual machines. They also broaden change management beyond baseline-only configuration. NERC lists the revised standards, including CIP-002-7 through CIP-013-3, as effective 1 July 2028, and the order does not require any entity to adopt virtualization. An entity that keeps physical, non-virtualized systems still has to read the revised text, because the new language applies to how its existing systems are described and monitored.
- Optional adoption: Adopting virtualization is optional. An entity that does not virtualize its BES Cyber Systems is not required to deploy a hypervisor or cloud-hosted control environment to meet these standards.
- Perimeter language: Review how your Electronic Security Perimeter and Physical Security Perimeter wording reads against the revised definitions, even if your architecture has not changed.
- Change management: Expect configuration change tracking to cover more than baseline-only changes once the revised CIP-010 language applies.
- Early adoption: Entities may adopt early after notifying their Regional Entity, at 6, 12 or 18 months after the order's effective date.
Confirm with your Regional Entity and your CIP Senior Manager which version of each standard applies to your systems on the date you plan to take action.
CIP-002-8 revises the Control Center definition and takes effect 1 July 2028. The change determines which facilities count as Control Centers for impact rating, so it decides whether some assets move into a different impact category. Entities that operate control functions at facilities they have not previously classified as Control Centers should treat this as a scoping task, not a paperwork update. The definition change flows into later requirements, including the CIP-015 timing for Control Centers and backup Control Centers.
- Scope review: Re-run your CIP-002 categorization against the revised definition before 1 July 2028.
- Backup facilities: Check backup Control Centers, since the CIP-015 dates differ for them.
- Impact changes: A facility reclassified under the revised definition can bring new BES Cyber Systems into high or medium impact requirements.
- Documentation: Update the categorization list, the CIP Senior Manager approval record and related evidence together.
- Dependencies: Map which asset owners, operators and vendors are affected by any reclassification.
Confirm with your Regional Entity how it expects the revised definition to be applied to your facility types before the effective date.
CIP-015-1 adds internal network security monitoring (INSM) inside the Electronic Security Perimeters of high and medium impact BES Cyber Systems. It takes effect 1 October 2028 for high and medium impact systems at Control Centers and backup Control Centers. Other medium impact systems with External Routable Connectivity are due within 24 calendar months after that date. This sequencing means Control Center operators face the first monitoring obligation, while other medium impact entities have a later deadline. Monitoring must be designed to detect anomalous activity between internal assets, not only at the perimeter.
- Control Centers first: High and medium impact systems at Control Centers and backup Control Centers carry the earliest deadline.
- Later medium impact scope: Other medium impact systems with External Routable Connectivity follow 24 calendar months later.
- Extension to EACMS and PACS: CIP-015-2, approved 10 August 2026, extends INSM to associated EACMS and PACS from 1 October 2029 and retires CIP-015-1.
- Low impact: CIP-015 does not apply to low impact BES Cyber Systems.
- Architecture: Confirm which network segments and sensors you can instrument inside the perimeter.
Confirm with your Regional Entity whether your Control Center and backup facilities fall within the first group, and check the CIP-015-2 implementation plan against your own schedule.
CIP-014-4 refines the physical security risk assessment under CIP-014 and takes effect 1 October 2028 under a 24-month implementation plan. It retires CIP-014-3. The revision applies to entities that own or operate Transmission stations and substations covered by the physical security standard. Its practical effect is on how the risk assessment is documented, reviewed and checked by a third party, so entities should expect to revisit their existing evaluations rather than start from zero.
- Timing: The revised standard takes effect 1 October 2028, and the prior version has an inactive date of 30 September 2028.
- Risk assessment: Review how threat and vulnerability evaluations are documented against the refined requirements.
- Third-party review: Confirm how your independent verification and review arrangements will meet the revised text.
- Physical security plan: Check that the physical security plan reflects the updated assessment results.
- Scope: CIP-014 applies to Transmission stations and substations, not to BES Cyber System impact categories.
Confirm the specific changes in the CIP-014-4 implementation plan with your Regional Entity before planning the revised assessment cycle.
CIP-003-11, approved in Order No. 918, adds remote user authentication, protection of authentication information in transit and malicious communication detection for low impact assets. It takes effect 1 July 2029. Low impact entities do not have to meet the high and medium impact requirements, but they must cover these new elements in their cyber security plan. The changes are narrower than the full CIP program, yet they reach the remote access paths that low impact entities use for maintenance and vendor support.
- Remote user authentication: Show how remote users authenticate to low impact BES Cyber Systems.
- Authentication in transit: Protect authentication information while it moves across networks.
- Malicious communication detection: Document how communications to and from low impact assets are monitored for malicious activity.
- Existing 2026 requirement: CIP-003-9, which covers vendor electronic remote access controls, became enforceable 1 April 2026 and sits alongside these changes.
- Plan updates: Revise the cyber security plan and its evidence before 1 July 2029.
Confirm with your Regional Entity whether your assets remain low impact after the CIP-002 review, because that determines whether these changes apply to you.
When early adoption of the virtualization standards makes sense
Early adoption makes sense when an entity is already changing its perimeter, change management or configuration tooling for virtualization, and wants those changes to be audited against one set of rules instead of two. Under NERC's implementation plan for the virtualization set, an entity may adopt the revised standards early, after notifying its Regional Entity, at 6, 12 or 18 months after the approving order's effective date of 26 May 2026. The standards otherwise take effect on 1 July 2028, so the early options fall well ahead of that date. Confirm the exact early adoption date for your entity with your Regional Entity before you plan a cutover, because the notice and the chosen date determine when the revised requirements start to bind.
The main benefit is a shorter period in which the organization must run two standard versions side by side. Until the revised standards are in force, procedures, baselines and evidence collection have to satisfy the current CIP-005, CIP-007, CIP-010 and CIP-013 requirements, while the team also prepares for the revised versions. Adopting early lets one set of procedures and evidence serve both the audit scope and the new language, at the cost of earlier work. Expect configuration changes to access control, change management baselines and vendor procedures, plus updated evidence for virtual machines and virtualization infrastructure, all completed before the adoption date. Entities that do not already virtualize, or that have no near-term plan to, gain little from early adoption and can use the time to build the procedures without a cutover.
Before committing, ask three questions. Which of your BES Cyber Systems, EACMS or PACS will run on virtualization infrastructure, and does the change touch Applicable Systems that are in scope today? Can your change management and baseline tooling produce the broader change evidence the revised standards describe within the time you have? Does your Regional Entity expect the notice, and does your implementation plan match the dates in NERC's CIP standards implementation documents? Entities that answer these questions early can choose between an early cutover and the standard 1 July 2028 date with a clear plan, and can scope any outside help against a written list of changes.
What to have in place before the 2028 deadlines
Six items need owners and dated evidence before the 2028 changes take effect. Most of them depend on one another, since the categorization sets which systems the virtualization inventory, the network map and the change process must cover.
Current CIP-002 categorization
Rerun the CIP-002 categorization against the revised Control Center definition in CIP-002-8, which takes effect 1 July 2028. Confirm which facilities and BES Cyber Systems change impact rating and record the bright-line basis for each change. The CIP Senior Manager approves the list. The auditor will ask for the dated approval, the per-asset analysis and the list of systems that changed since the last review.
Virtualization infrastructure inventory
Build an inventory of hypervisors, management planes, container hosts and the virtual machines that host BES Cyber Systems, EACMS, PACS and PCAs. The virtualization revisions, including CIP-002-7 and CIP-010-5, apply from 1 July 2028, but they do not require virtualization, so record which systems run virtualized and which do not. The OT infrastructure lead owns the inventory, and the auditor will ask for the system-to-host mapping and its change history.
Electronic Security Perimeter network map
Draw current network diagrams that show every Electronic Security Perimeter, Electronic Access Point, Intermediate System and the traffic flows inside each perimeter. CIP-015-1 places INSM sensors inside these perimeters, so the map decides where monitoring can sit at high and medium impact sites with External Routable Connectivity. Network engineering owns the diagrams with OT security. The auditor will ask for diagrams tied to the asset inventory and a record of the last review.
Change management beyond baselines
Update the change process to cover virtualization activities, such as moving or cloning virtual machines, changing hypervisor settings and altering virtual network paths. Order No. 919 broadened change management to more than baseline configuration, and CIP-010-5 applies from 1 July 2028. The change advisory board chair owns the procedure with the CIP Senior Manager. The auditor will ask for the revised procedure, change tickets showing approval and verification, and configuration monitoring records.
CIP-014-4 risk assessment review
Set a review cycle for the physical security risk assessment of critical Transmission stations and substations that follows CIP-014-4 as written. That version takes effect 1 October 2028 and retires CIP-014-3, so confirm the third-party verification and third-party review steps are scheduled and that the reviewer is independent of the team that wrote the plan. The physical security manager owns the assessment with the CIP Senior Manager. The auditor will ask for the dated assessment, verifier reports and plan revision history.
Dated plan for inactive dates
Map each standard listed as inactive on 30 June 2028 (CIP-002-5.1a, CIP-003-9, CIP-004-7, CIP-005-7, CIP-006-6, CIP-007-6, CIP-008-6, CIP-009-6, CIP-010-4, CIP-011-3 and CIP-013-2) and CIP-014-3, which is inactive on 30 September 2028, to its replacement and the date that replacement takes effect. Assign a named owner for each standard, schedule gap assessments and hold a go or no-go review before the first inactive date. The CIP Senior Manager and the compliance program lead own the plan. The auditor will ask for the signed plan, gap assessment results and approved procedure revisions.
Choosing between an early adoption path and waiting for the effective date
This table compares adopting the virtualization standards early, at a supported 6, 12 or 18 month point after Order No. 919's effective date, with waiting for the 1 July 2028 effective date. Read each row as a decision factor, and treat the early path as a commitment to confirm with your Regional Entity before any work starts.
| Decision factor | Adopt early (6, 12 or 18 months) | Wait for 1 July 2028 |
|---|---|---|
| When it fits | Entities already planning virtualized EACMS, PACS or Control Center changes, or that want new change management language in place before a scheduled refresh | Entities with no near-term virtualization plans that want to keep the current baseline-only change process until the standards are required |
| Notice required | Notify the Regional Entity before adopting early, as NERC's implementation plan requires | No notice needed, but confirm the Regional Entity's expectations for the transition period |
| Internal staff effort | Update CIP-002, CIP-005, CIP-007 and CIP-010 procedures, train affected staff and document the new baselines and change tracking earlier | Spread the same work over a longer runway, with less pressure on the CIP Senior Manager and delegates in 2027 and 2028 |
| Configuration and change records | Start recording virtual machine and virtualization infrastructure baselines sooner, which creates evidence history before an audit | Begin baseline records near the effective date, leaving less time to show a stable pattern |
| Dependency on other timelines | Must sequence with the CIP-002-8 Control Center definition change also effective 1 July 2028 | Same 2028 dependency, but with fewer intermediate changes to coordinate |
| Confirm before choosing | Which adoption point the Regional Entity accepts, the exact notification steps, and whether any early adopted version creates interim obligations | Whether any interim monitoring or data requests from the Regional Entity will reference the virtualization revisions before the effective date |
| Reversibility | Harder to reverse once adopted and reported, so decide with the CIP Senior Manager and compliance lead | Keeps options open until the effective date, but leaves less time to fix gaps |
Where NERC CIP timelines usually slip
Most CIP schedule problems come from reading the timeline as a list of dates rather than a set of linked decisions. The cards below cover the five gaps we see most often, and each one names the check that keeps a program on schedule through 2029.
Treating 2026 versions as optional
CIP-003-9 became enforceable on 1 April 2026, and CIP-012-2 became enforceable on 1 July 2026. Entities with low impact assets sometimes postpone the vendor electronic remote access controls in CIP-003-9 because the audit feels distant, but enforcement does not wait for a schedule that suits the program. Confirm now which of your assets carry vendor remote access, and confirm that CIP-012-2 availability protections exist for Real-time data between Control Centers.
Missing superseded standard inactive dates
NERC lists 30 June 2028 as the inactive date for several current standards, including CIP-002-5.1a, CIP-003-9 and CIP-013-2, and 30 September 2028 for CIP-014-3. Teams that track only the new versions can lose track of which evidence set governs an audit period that spans the changeover. Build a version map that shows each requirement, its current version, its successor and the date the predecessor goes inactive.
Assuming CIP-015-2 matches CIP-015-1
CIP-015-1 covers internal network security monitoring inside the Electronic Security Perimeters of high and medium impact BES Cyber Systems. CIP-015-2, approved by FERC on 10 August 2026, extends that monitoring to associated EACMS and PACS from 1 October 2029 and retires CIP-015-1. Projects that design monitoring only for BES Cyber Systems will need a second phase for access control and physical access systems, so scope the monitoring architecture for both versions from the start.
Underestimating INSM network design work
Internal network security monitoring requires sensors, collection points and data paths inside each Electronic Security Perimeter, and many of these run through networks that were never designed for passive taps or mirrored traffic. Design decisions about segmentation, storage location and access to monitoring data take longer than the procurement cycle. Start the network survey and architecture review well before 1 October 2028, and confirm with your Regional Entity how the CIP-015-1 implementation plan applies to your Control Center and medium impact systems.
Assuming virtualization must be adopted
The virtualization revisions in Order No. 919 do not require entities to adopt virtualization. They update perimeter-based language, add terms for virtualization infrastructure and virtual machines, and broaden change management beyond baseline-only configuration. Entities that run only physical systems still need to confirm that the 2028 standards do not change their obligations in ways they must document, and should decide whether early adoption at 6, 12 or 18 months is worth notifying the Regional Entity.
Who owns the CIP timeline, who prepares the work and who audits it
The registered entity owns its CIP obligations for the whole timeline, from the first-day compliance dates to the retirement of superseded versions. Its CIP Senior Manager approves the policies, the categorization of BES Cyber Systems and the decision to adopt a revised standard early. Adoption timing for the 2028 virtualization set is one example: entities may adopt early after notifying their Regional Entity, at 6, 12 or 18 months after the order's effective date, and that choice belongs to the entity alone.
- Timeline decisions: The entity decides whether to adopt the July 2028 virtualization standards early and whether to plan for the October 2028 INSM and CIP-014 changes on their listed dates.
- Categorization and scope: The entity confirms which assets are high, medium or low impact under CIP-002 and which changes therefore reach its systems.
- Policy and delegation: The CIP Senior Manager signs off on policy, delegations and the cyber security plans that revised standards require.
- Evidence ownership: The entity keeps the evidence that shows compliance and presents it to the auditor.
- Vendor oversight: The entity stays accountable for any partner's work and for the CIP-013 supply chain plan.
Confirm with your CIP Senior Manager which inactive dates and effective dates apply to each standard in your environment before scheduling any project work.
An implementation partner such as DeployOpen prepares systems, configurations, INSM design and evidence so the registered entity can show compliance. Work is normally fixed in scope, with deliverables and timelines agreed in writing before work starts. The partner does not decide what the entity is required to do, does not sign compliance statements for the entity and does not issue reports or certificates. DeployOpen does not guarantee an audit result.
- Scoped preparation: Typical work includes readiness assessments against the 2026 to 2029 changes, configuration baselines, INSM architecture and evidence packages, written in a statement of work.
- Self-hosted platforms: Work can run inside the entity's own infrastructure, so BES Cyber System Information stays under the entity's control.
- Documentation handover: Deliverables should include the procedures and evidence index the entity's own staff can maintain after the project.
- Ongoing support: Retainers can cover upgrades and recurring tasks, scoped separately from the initial project.
- Access rules: Partner staff who reach BES Cyber Systems or BCSI must meet the entity's personnel risk and training requirements.
Ask any partner for a written scope that names the standards and dates it covers, and confirm that the entity retains accountability for every control.
The Compliance Enforcement Authority, which is a Regional Entity or NERC, monitors compliance with the CIP standards. It uses tools such as Compliance Audits, Spot Checks, Self-Certifications, Self-Reports, self-logging and periodic data submittals. Under the NERC Rules of Procedure, Balancing Authorities, Reliability Coordinators and Transmission Operators receive a Compliance Audit at least once every three years, while other registered entities are audited on a risk-based schedule set by the Regional Entity.
- Monitoring and findings: Auditors assess evidence against each applicable requirement and issue findings through the audit process.
- Enforcement: Penalties and sanctions follow the NERC Sanction Guidelines, and the statutory maximum is $1,584,648 per violation, per day, as adjusted by FERC Order No. 906 and shown in the eCFR.
- No certificate: There is no CIP certificate, so no consultant, partner or certification body can issue one.
- Version-specific review: Auditors test the version of each standard in force on the date of the audit period.
- Early adoption notice: Entities that adopt early must notify their Regional Entity, which is a point the auditor will check.
Confirm your Regional Entity, your audit schedule and which standard versions apply to you before planning evidence collection.
Common questions about NERC CIP changes through 2029
Which NERC CIP standards are enforceable in the United States today?
As of 17 October 2026, NERC lists 13 CIP standards as mandatory and enforceable in the United States: CIP-002-5.1a, CIP-003-9, CIP-004-7, CIP-005-7, CIP-006-6, CIP-007-6, CIP-008-6, CIP-009-6, CIP-010-4, CIP-011-3, CIP-012-2, CIP-013-2 and CIP-014-3. Two versions became enforceable in 2026: CIP-003-9 on 1 April 2026, which adds vendor electronic remote access controls for low impact BES Cyber Systems, and CIP-012-2 on 1 July 2026, which adds protection of the availability of Real-time data between Control Centers. Confirm the current list on the NERC CIP standards page, because standards are retired and replaced as new versions take effect.
Is virtualization mandatory under the CIP standards?
No. The virtualization revisions approved in FERC Order No. 919 do not require an entity to adopt virtualization. They update perimeter-based language, add terms for virtualization infrastructure and virtual machines, and broaden change management beyond baseline-only configuration. NERC lists the revised set, including CIP-002-7 and CIP-013-3, as effective 1 July 2028. Entities that choose to adopt early can do so at 6, 12 or 18 months after the order's effective date, after notifying their Regional Entity. An entity running traditional hardware can plan for the 2028 date without changing its architecture, but it should confirm with its Regional Entity how the revised language applies to its specific systems.
Must an entity adopt CIP-015 before the 2028 deadline?
No. CIP-015-1 has a future enforcement date of 1 October 2028 for high and medium impact systems at Control Centers and backup Control Centers, with other medium impact systems with External Routable Connectivity due 24 calendar months after that. Entities cannot be required to comply earlier than these dates under the approved standard, but they can plan early work such as network baselining, asset inventory of the internal network and sensor placement. Confirm the exact applicability of each system category with the implementation plan and your Regional Entity before setting an internal schedule.
How should an entity choose between planning for CIP-015-1 and CIP-015-2?
Plan against CIP-015-2 if your associated EACMS and PACS are in scope, because it extends internal network security monitoring to those systems from 1 October 2029 and retires CIP-015-1. CIP-015-2 was approved by FERC on 10 August 2026, and its dates are offset 12 months from the CIP-015-1 dates. Plan first for CIP-015-1 at the 2028 dates for your high and medium impact Control Center and network systems, then add EACMS and PACS coverage in your 2029 work. Confirm the version and retirement mapping in the CIP-015-2 implementation plan, and ask whether your monitoring architecture can later extend to access control and physical access systems without a redesign.
What does a consultant do for the NERC CIP timeline?
A consultant helps you map each approved standard, its effective date and its inactive date onto your own BES Cyber Systems, then builds a schedule of technical and documentation work. Typical tasks include reviewing categorization under CIP-002, planning monitoring and baseline changes, updating policies and evidence procedures, and preparing a readiness plan for each change. The consultant does not own compliance, does not decide applicability for the entity, and cannot issue an audit finding. The CIP Senior Manager remains accountable, and the Regional Entity makes the compliance determination.
Can a partner like DeployOpen do the CIP change work internally for us?
DeployOpen can plan, implement, document and support self-hosted open-source platforms inside your own infrastructure, which can include the technical systems and evidence that CIP work depends on. Most engagements are fixed-scope, with deliverables and timelines agreed in writing before work starts. DeployOpen does not act as your CIP Senior Manager, does not issue compliance reports, and does not replace the Regional Entity's monitoring role. Your staff keep control of the program, and you should confirm with your Regional Entity which tasks must remain with registered personnel. Ask for a written scope that lists each system, each standard and each evidence item covered.
How much does NERC CIP change work cost?
Cost depends on scope and the number of BES Cyber Systems, their impact ratings, the number of Electronic Access Points and Control Centers involved, and whether you need new monitoring or only documentation changes. One-time costs usually include planning, technical changes, testing and documentation updates. Recurring costs include evidence collection, periodic reviews and staff time for each CIP cycle. DeployOpen does not publish a price list, and a quote follows from a written scope. Ask any provider for a breakdown by standard, by system group and by one-time versus recurring work, and for the assumptions behind each line. FERC's published paperwork estimates for new standards are a useful input, and you should check the current figures in the relevant FERC orders.
How DeployOpen works on this
DeployOpen helps registered entities turn the CIP effective dates through 2029 into a written scope, a build plan and evidence they can hand to their CIP Senior Manager. We prepare systems, controls and documentation inside your own infrastructure, while your organization keeps ownership of its compliance program and the Regional Entity keeps its audit role.
How we scope
- Map each CIP standard with a 2026, 2028 or 2029 change against your current BES Cyber System categorization and applicable systems.
- Confirm with your Regional Entity and CIP Senior Manager which effective dates and early adoption options apply to your assets.
- Agree a fixed-scope written statement of work covering systems, deliverables, timelines and the owner for each decision before work starts.
How we build
- Prepare virtualized environments and perimeter documentation for the 2028 virtualization standards in your own cloud accounts, data centers or air-gapped networks.
- Design internal network security monitoring for CIP-015 scope, documenting sensor placement and data retention for review against the 2028 and 2029 dates.
- Test configuration, backup and recovery changes in a staging environment before they touch BES Cyber Systems, and record the results as evidence.
How we hand over
- Deliver a dated change register listing each standard revision, its effective date, affected controls and the evidence each one will need.
- Document system configurations, runbooks and evidence locations so your staff can produce records during a Compliance Audit or Spot Check.
- Transfer administration of every system to your team with written procedures, and confirm the handover in the agreed statement of work.
How we support
- Offer ongoing support, upgrades and continuous testing as a retainer after the fixed-scope work closes.
- Review the change register whenever FERC approves a new CIP revision or NERC updates an implementation plan.
- Confirm with your CIP Senior Manager that the Regional Entity, not DeployOpen, decides audit outcomes and any penalty or mitigation questions.
Sources and further reading
- NERC CIP Reliability Standards ↗
- FERC Order No. 919, Virtualization Reliability Standards ↗
- FERC Order No. 918, Reliability Standard CIP-003-11 ↗
- Project 2023-03 INSM, CIP-015-1 implementation plan ↗
- Project 2025-02 INSM, CIP-015-2 implementation plan ↗
- Project 2023-06 CIP-014 risk assessment refinement, CIP-014-4 implementation plan ↗