When does the EU Cyber Resilience Act timeline bite for our products?
The Cyber Resilience Act entered into force on 10 December 2024, Article 14 reporting obligations apply from 11 September 2026, and the regulation applies in full from 11 December 2027. If your company sells products with digital elements in the EU, the first date that may already bite is the reporting duty, because it reaches products regardless of when they were placed on the market. The full set of Annex I requirements and conformity assessment obligations follows on 11 December 2027, but only for products placed on the market from that date or products substantially modified from that date. Reporting is the date to plan around first.
Which date applies to a given product depends on three questions. First, when was it placed on the market, since products already sold before 11 December 2027 are covered only if they are substantially modified from that date, while Article 14 still reaches them. Second, what your role is: manufacturer, importer, distributor or open-source software steward, because each carries different duties and the steward regime is lighter. Third, whether an update changes the product enough to count as a substantial modification. Confirm each answer in writing for every product family before you assign a deadline, since a single product line can have several dates depending on its release history.
Chapter IV, on the notification of conformity assessment bodies, applies from 11 June 2026. It matters mainly to Member States and to conformity assessment bodies that want to be notified, but it also affects manufacturers who need a notified body for important or critical products, because capacity depends on how quickly authorities designate them. Ask prospective notified bodies whether they hold a notification for the relevant product category and when they expect capacity to be available. The timing of standards and guidance should be checked against the current Commission and ENISA pages before you commit to a plan, because several dates in this area have moved in recent months.
Which CRA dates have already passed and which are still ahead
The sequence runs from signature in October 2024 to full application in December 2027, and it shows which obligations are already in force and which are still ahead. Each step names the legal trigger, the governing article and whether it has passed as of this page's date. Reporting has already started, so the reporting process should be in place before the product rules apply.
Record the signature on 23 October 2024
Passed. Regulation (EU) 2024/2847 was signed on 23 October 2024. The signature fixed the legal text but placed no direct duties on manufacturers, importers or distributors. Record the date in your compliance register as the starting point for the legislative timeline, and cite the regulation by its number in internal documents. The Commission's policy page for the Cyber Resilience Act gives the official overview.
Confirm publication in the Official Journal
Passed. The regulation was published in the Official Journal on 20 November 2024. Publication is the legal event that starts the countdown to entry into force, because Article 71(1) counts from publication. Confirm the citation against the consolidated text on EUR-Lex and store the official reference, so that every later date in your plan traces back to a published source.
Track entry into force on 10 December 2024
Passed. The regulation entered into force on 10 December 2024, the twentieth day after publication under Article 71(1). Entry into force makes the regulation part of EU law, and it sets the reference dates for the phased application that follows. Most product duties do not apply yet, so this step is the point to start the scope analysis and the inventory of products with digital elements.
Confirm Chapter IV applied on 11 June 2026
Passed. Chapter IV, covering the notification of conformity assessment bodies in Articles 35 to 51, applied from 11 June 2026, under Article 71(2). Member States were to have designated their notifying authorities by then. Check whether your Member State has designated authorities, and review the Commission's NANDO database, which lists the notified bodies, before you contact any body about a third-party assessment.
Meet Article 14 reporting from 11 September 2026
Passed. Manufacturers' duty to notify actively exploited vulnerabilities and severe incidents under Article 14 has applied since 11 September 2026. ENISA launched the initial operating capability of its Single Reporting Platform the same day, and notifications go to the CSIRT designated as coordinator. This duty covers in-scope products placed on the market at any time, under Article 69(3). Confirm that you have a documented reporting procedure, a named owner and a tested route into the platform. The ENISA launch announcement describes the platform.
Watch the 11 December 2026 notified body milestone
Upcoming. The Commission's implementation timeline, updated on 27 July 2026, sets 11 December 2026 as the milestone for sufficient notified bodies across Member States. This is a planning target, not the date on which product obligations apply. The same timeline plans a delegated act on presumption of conformity for the EUCC certification scheme in the fourth quarter of 2026. Ask any conformity assessment body you consider whether it is designated for your product class and when its capacity is confirmed.
Prepare for full application on 11 December 2027
Upcoming. The regulation applies in full from 11 December 2027, including the obligations of open-source software stewards, under Article 71(2). Products placed on the market before that date fall under the regulation only if they are substantially modified from it, under Article 69(2). Before this date, finish the risk assessment, technical documentation, support period definitions and EU declaration for each product that will be in scope, and record which products are likely to be substantially modified.
Which implementing and delegated acts already shape the plan
Several Commission acts and guidance documents already set how the Cyber Resilience Act is read and applied. Each one changes a different part of a manufacturer's plan, from how products are classified to how far ahead rule changes must be announced. Check each one against your product line before fixing scope, documentation and reporting procedures.
Product categories under Implementing Regulation 2025/2392
Implementing Regulation (EU) 2025/2392, adopted on 28 November 2025, gives the technical description of each important and critical product category listed in the annexes. It decides whether a product is default, important class I or II, or critical, and that decision sets the conformity assessment route. Map each product line to its category description now, because a wrong classification changes whether self-assessment is enough or a notified body is needed.
Delayed notification dissemination under 2026/881
Delegated Regulation (EU) 2026/881 sets when CSIRTs may delay passing on notifications under Article 14(9). It does not change what a manufacturer must report, but it affects what happens after a report reaches the authorities. Confirm internally who receives updates from the CSIRT, and keep your own record of when each notification was sent so that your timeline can be reconstructed if an authority asks.
Non-binding guidance under C(2026) 5252
The Commission's guidance of 27 July 2026, annexed to Communication C(2026) 5252, is non-binding but shows how the Commission reads scope, free and open-source software, substantial modification, support periods and risk assessment. Use it to test your interpretations, especially where your product is a component supplied to others. Record which guidance section supports each scoping decision so that the reasoning can be shown to an assessor or market surveillance authority.
Commission FAQ version 1.4
Version 1.4 of the Commission's CRA FAQs, dated 4 September 2026, answers practical questions on classification, conformity routes and harmonized standards. FAQs are not law, yet they are the quickest guide to how the Commission expects questions to be answered. Review the version date when you file your interpretation log, and re-check any position you took under an earlier version, since answers can change between versions.
EUCC presumption of conformity act
The Commission's implementation timeline planned a delegated act giving presumption of conformity for products certified under the EUCC scheme, targeted for the fourth quarter of 2026. If your product already holds or is pursuing EUCC certification, this act could change the route you rely on for Annex I evidence. Ask your certification body whether its scope covers the Annex I requirements, and track the act's final text before you commit to a certification path.
Notice periods for future delegated acts
Future delegated acts that add Annex III categories or move them to class II should give at least 12 months before the new procedures apply. Delegated acts requiring certification of critical products should give at least six months, unless urgency justifies less. These notice rules set the minimum lead time you have to adjust a product's route after a classification change. Build a watch on the Official Journal into your product governance, and assign an owner to review any new act within weeks of publication.
How harmonized standards deadlines affect the conformity route
Harmonized standards decide how much of the conformity route a manufacturer can handle alone. Under the Cyber Resilience Act, most products follow self-assessment under module A, and a product can stay on that route only if the harmonized standards covering its requirements are applied in full. Commission standardization request M/606 asks the European standardization organizations for 41 harmonized standards: 15 horizontal standards grouped in three deliverables, and 26 product-specific standards. The Commission's FAQ 6.10 sets the deadlines: 30 August 2026 for the risk-based design and vulnerability handling horizontal standards, 30 October 2026 for the 26 vertical standards, and 30 October 2027 for the Annex I Part I horizontal standard. Where a standard is missing, late or only partly applied, the manufacturer has to show how it met the Annex I requirements another way, and a notified body may be needed for class I important products.
The practical question is which standards cover your product and whether each one has been published and cited in the Official Journal at the time you rely on it. Map every Annex I requirement in your risk assessment to a standard, then record the status of each one on the date you make your conformity decision. Keep that record with your technical documentation, because a delayed standard can move a class I important product from self-assessment toward a notified body route, and the difference affects your schedule and budget. Ask any notified body or consultant to state in writing which standards they treat as applied in full for your product type, and which requirements they would test without one.
Confirm the current status of each standard before relying on any date in this section. The official sources are the Commission's CRA pages, the Commission FAQs (version 1.4 is the one referenced here) and the standardization request and status listings published by the European standardization organizations. Dates can move, and the Commission's implementation timeline, updated 27 July 2026, also planned a delegated act on presumption of conformity for the EUCC certification scheme for the fourth quarter of 2026. Recheck these sources at each milestone and before any declaration of conformity is signed, since the status on the day you rely on a standard is what an assessor will examine.
What applies to a product placed on the market before December 2027
Under Article 69(2), a product with digital elements placed on the market before 11 December 2027 falls under the regulation only if it is substantially modified from that date. A product that was already sold and is not changed in a way that counts as substantial stays outside the essential requirements of Annex I and the conformity assessment duties. This transitional rule protects installed products from retroactive redesign, but it does not remove every obligation, as the next tab explains.
- Placement date: the relevant date is when the product was first made available on the EU market, not when it was designed or last released.
- No substantial modification: routine maintenance and security patches generally do not reset the product into scope, although the Commission guidance should be checked for borderline cases.
- No new CE marking duty: a product in this group does not need a new EU declaration of conformity solely because the regulation now exists.
- Documentation of the decision: keep a dated record of why each product was or was not treated as substantially modified.
- Interface with other law: confirm that other Union harmonization legislation applied to the product still treats it as compliant.
Before relying on this route, ask counsel or your market surveillance contact to confirm how the product's update history will be judged.
A product placed on the market before 11 December 2027 comes under the regulation from the point it is substantially modified on or after that date. At that point the modified product is treated as a product placed on the market, so the Annex I requirements, the risk assessment, the support period and the conformity assessment route all apply to it. The trigger is the modification, not the original sale, which means a legacy product can move into scope through a single release.
- Trigger on or after 11 December 2027: a change made before that date does not bring the product into scope under this rule.
- Judgment on substance: the Commission guidance and its examples explain what counts as a substantial change, and the question should be settled per product family.
- New obligations follow: a new conformity assessment, a new support period and technical documentation are required once the product is in scope.
- Parallel product lines: check whether a release on a legacy branch could be treated as a new product version.
- Record keeping: keep release notes and change assessments that show the reasoning behind each decision.
Illustratively, a firmware overhaul released in early 2028 that changes core functionality may bring an older device into scope, while a patch fixing a known flaw usually would not. Confirm each case against the guidance before release planning.
The transitional rule does not apply to reporting. Under Article 69(3), the Article 14 duty to notify actively exploited vulnerabilities and severe incidents covers all in-scope products whenever they were placed on the market. Reporting obligations began on 11 September 2026, so an older product that is in scope of the regulation can trigger a notification today even though its full essential requirements are not yet due.
- Start date: Article 14 has applied since 11 September 2026, the day ENISA launched the initial operating capability of the Single Reporting Platform.
- Scope of the duty: it covers the product as an in-scope product, so the first step is deciding whether the product is in scope at all.
- Recipient: notifications go to the CSIRT designated as coordinator, and ENISA receives them at the same time through the platform.
- Preparation gap: a manufacturer may need a working process to detect and report exploited vulnerabilities well before the full regulation applies.
- Vulnerability handling: the processes that support reporting also serve the eight Annex I Part II requirements that apply later.
Confirm with your national CSIRT or ENISA's platform guidance which contacts and procedures are in place for your product type.
Products already covered by cybersecurity certification under other Union harmonization legislation are handled differently. Under Article 69(1), EU type-examination certificates on cybersecurity issued under that legislation remain valid until 11 June 2028, unless they expire earlier. The certificate is therefore a bridge rather than a permanent exemption, and manufacturers should plan for what happens when it lapses.
- Validity date: the certificate stays valid until 11 June 2028 or its own expiry, whichever is earlier.
- Check the expiry: the certificate's own expiry date governs if it falls before that milestone.
- Plan the successor route: decide early whether the product will move to the CRA conformity assessment route before the bridge ends.
- Scope of the bridge: confirm with the certifying body which Union legislation issued the certificate and whether it covers the whole product.
- Evidence trail: keep the certificate, its scope statement and any amendments with the technical file.
Ask your notified or certifying body to confirm the validity period and whether any extension or transition arrangement applies to your certificate.
What happens after full application, through 2028 and 2030
The timeline does not end at full application on 11 December 2027. Three review points follow, and each can change how the regulation is read in practice. The first is the Commission's report on the effectiveness of the CRA Single Reporting Platform, due by 11 September 2028 under Article 70. Because the platform went live with an initial operating capability on 11 September 2026, that report will be the first formal look at whether manufacturer notifications, CSIRT routing and ENISA access work as designed. Manufacturers that have been filing Article 14 notifications since 2026 should keep a record of their own reporting experience, including delays, unclear CSIRT routing and questions the platform did not answer, so they can judge whether the process they built still fits.
The second point is ENISA's first technical report on emerging cybersecurity risk trends in products, required under Article 17(3) within 24 months of the date reporting obligations started to apply, and then every 24 months. Read against the start of reporting on 11 September 2026, that first report falls in the period leading into 2028. Its findings could shape how authorities and manufacturers judge what counts as a reasonable risk assessment for particular product types. The Commission's full evaluation of the regulation follows by 11 December 2030 and every four years after that. Teams should ask who inside their organization owns tracking these outputs, and how often guidance, FAQs and standards are checked against the product documentation they already maintain.
The practical lesson is that the regulation is not a fixed final state. Commission guidance, the FAQs and harmonized standards may be revised after publication, and delegated acts can add or move product categories, with advance notice periods that Articles 7(3) and 8(1) set out. Compliance files should therefore record the version of the guidance and standards relied on at each decision point, so that changes can be assessed without reopening settled questions. Organizations should confirm with their notified body, their national market surveillance authority or their legal counsel how each review outcome applies to their product families before budgeting for later years.
What to check now given the dates already in force
Reporting duties under Article 14 already apply, and the substantial modification test runs from 11 December 2027. The cards below connect those two dates to the checks that need an owner and a record now, not in 2027.
Confirm reporting duties reach your products
Article 14 reporting applies to all in-scope products whenever they were placed on the market, so the 11 September 2026 start date is not a future deadline for any product you already sell. Start with a list of in-scope products and check whether any of them has actively exploited vulnerabilities or severe incidents that you have not yet assessed. Record the date you completed the check and who signed it off. Illustrative: a product sold since 2023 falls under reporting even though its full obligations wait until 2027.
Identify your CSIRT and platform route
Notifications go to the CSIRT designated as coordinator in the Member State concerned, and ENISA receives them at the same time through the Single Reporting Platform. Confirm which CSIRT your products route to, then establish who in your organization holds the account credentials and who can submit within the 24-hour early warning window. Check the ENISA launch notice for the current access model before you assume an account can be created on demand. Ask your coordinator which contact channel it accepts outside business hours.
Inventory products placed on the market
Products placed on the market before 11 December 2027 fall under the full regulation only if they are substantially modified from that date. That makes the release history of each product family a compliance record, not just an engineering one. List each product with its first market placement date, current version, support end date and any planned changes. Mark products that will need a new conformity assessment if modified after the cut-off, so that engineering planning can account for them.
Map substantial modification risk for releases
Before each upcoming release, decide whether the change could be a substantial modification, since that step can bring a legacy product into full scope. The Commission's guidance covers the examples and the reasoning, and security updates usually do not trigger reassessment. Put this decision in the release checklist with a named reviewer and keep the written rationale. Flag releases planned close to 11 December 2027 for legal review, because a change shipped just before or after that date can have different consequences.
Track harmonized standards deliverables
The standardization request M/606 sets deliverable dates for the harmonized standards: 30 August 2026 for the risk-based design and vulnerability handling horizontal standards, 30 October 2026 for the product-specific standards, and 30 October 2027 for the Annex I Part I horizontal standard. Assign someone to check the status of each deliverable at each milestone and note which standards your products would rely on for presumption of conformity. Confirm with your notified body or assessor whether they will accept a standard still in development.
Set internal owners for each duty
Reporting, risk assessment, technical documentation, vulnerability handling and the EU declaration each need a named owner with authority to act. Without owners, the 24-hour early warning and the 72-hour follow-up can stall between product, security and legal teams. Write a RACI for each duty, confirm who can approve an external notification, and test the escalation path with a tabletop exercise. Record the owner in the same register as the product inventory so that evidence can be traced later.
Who owns each deadline and who helps meet it
The organization placing products on the EU market owns its obligations under the Cyber Resilience Act, and that ownership does not transfer to any outside party. Its legal role (manufacturer, importer, distributor or steward) determines which dates apply to it, and it alone decides how it classifies its products, what its risk assessment concludes and what it reports to authorities.
- Role and scope decisions: Confirm whether each product is in scope and which economic operator role the organization holds for it.
- Reporting decisions: Decide whether an event meets the Article 14 threshold and submit the notification through the ENISA platform under its own authority, from 11 September 2026.
- Declarations and CE marking: Sign the EU declaration of conformity and affix CE marking once conformity is demonstrated.
- Support period commitments: Set and publish the support period for each product and staff the vulnerability handling process that runs for it.
- Records: Keep technical documentation and records available to market surveillance authorities.
Before any deadline, check that a named executive owns each of these decisions in writing.
An implementation partner such as DeployOpen prepares the systems, documentation and evidence that support the organization's decisions. Its work is delivered inside the client's own infrastructure and is governed by a written scope, so the partner supplies material for the organization to review and adopt rather than acting as the regulated party.
- Systems and build pipelines: Harden self-hosted build, update and vulnerability management tooling so the controls exist before they are needed.
- Documentation drafts: Prepare technical documentation, risk assessment write-ups and vulnerability handling procedures for internal approval.
- Evidence collection: Gather logs, SBOM outputs, test results and configuration records that show how controls operate.
- Testing: Run security testing of products and their components so findings feed the risk assessment.
- Scope limits: The partner cannot submit Article 14 notifications, sign declarations or act as the organization's authorised representative unless the organization gives that authority in a separate, written arrangement with its own legal review.
Ask for the written scope to state which artifacts the partner produces and which steps remain with the organization.
Only an independent conformity assessment body issues certificates or conformity findings. For most products the manufacturer self-assesses under module A. A notified body is needed for class I important products where harmonized standards are not applied in full, and for class II and critical products, according to the Commission's FAQ. Member States notify these bodies, and they are listed in the Commission's NANDO system.
- Notification timing: Chapter IV, covering notified bodies, applies from 11 June 2026, and the Commission's milestone for enough notified bodies is 11 December 2026.
- Independence: The body assesses the product and documentation on its own judgment and is not a consultant to the same manufacturer.
- Certificates: Only the body issues the certificate in the routes that require one.
- Reporting: A notified body does not file the manufacturer's Article 14 reports.
- Selection: Confirm the body's notification scope in NANDO for the relevant product category before engaging it.
Check that any body you engage is listed for the correct category and that its scope covers your product before you commit to a timeline.
Where CRA timelines usually slip
Most CRA delays come from misreading dates, waiting for outputs that have not yet arrived, and assuming older products or earlier guidance still hold. Each pattern below has a specific check that can be done this quarter, before the next release gate.
Treating 2027 as the first deadline
Many teams plan around the full application date of 11 December 2027 and leave everything earlier for later. Article 14 reporting has applied since 11 September 2026, covering actively exploited vulnerabilities and severe incidents for in-scope products on the market, whatever their placing date. Check now which products are in scope, who acts as manufacturer, which CSIRT is the coordinator, and who can send an early warning and notification on a weekend or during leave.
Waiting for all standards
Commission standardization request M/606 asks for 41 harmonized standards, with deliverables due on 30 August 2026, 30 October 2026 and 30 October 2027. Teams often hold the risk assessment until these arrive, which pushes design work into the final months before application. The risk assessment is the manufacturer's own obligation and can start now from the Annex I essential requirements. Start the assessment now and revise it as each standard is published, recording which requirements a standard covers and which the team meets by its own methods.
Underestimating legacy products
Products already on the market before 11 December 2027 fall under the regulation only when they are substantially modified after that date. The trap is assuming that makes them out of scope altogether. Article 14 reporting still applies to them, so a product sold in 2025 can trigger a notification duty in 2026 if it has an actively exploited vulnerability. Build an inventory of every shipped and installed version, mark each as modified or unmodified, and confirm who owns vulnerability reports for older releases.
Relying on outdated guidance
Interpretations have moved during 2026. The Commission published non-binding guidance on 27 July 2026 covering scope, free and open-source software, substantial modification, support periods and reporting. Design decisions based on earlier drafts, conference slides or vendor summaries may no longer match it. Date every interpretation in the technical file, and recheck the Commission guidance and FAQs before each release gate so the file records which version was applied.
Skipping notified body capacity checks
Class II and critical products need a notified body, and the Commission's implementation timeline set 11 December 2026 as the milestone for sufficient notified bodies across Member States. Chapter IV applied from 11 June 2026, so designations are still being built out. Ask each candidate body for its designation scope and written lead times before fixing a release plan, and confirm in the Commission's NANDO system that the body is listed for the relevant CRA product category.
Questions buyers ask about the CRA timeline
Does CRA reporting really apply before full application in December 2027?
Yes. The Article 14 reporting obligations apply from 11 September 2026, while the rest of the regulation applies from 11 December 2027. Manufacturers must notify actively exploited vulnerabilities and severe incidents for in-scope products, and this duty applies to products placed on the market before 2027 as well. ENISA's Single Reporting Platform went into initial operating capability on the same day reporting began, so the reporting route already exists. Confirm the exact scope of Article 14 against the regulation text on EUR-Lex before you design your process, because the reporting duty does not wait for the full set of Annex I requirements.
- Reporting duty: from 11 September 2026
- Full application: from 11 December 2027
- Notification route: the ENISA platform and the designated CSIRT
What drives the cost of starting CRA work now?
The cost depends on how many products you have, how much of their code and components you already understand, and how mature your vulnerability handling is today. The main cost components are internal engineering time, legal and product classification review, security testing, documentation of the risk assessment, and any third-party conformity assessment your product class requires. Some costs are one-time, such as the first risk assessment and technical documentation, while others recur, such as vulnerability monitoring and maintaining documentation over the support period. Ask any partner for a fixed-scope quote that lists products, deliverables and assumptions in writing. For published estimates of compliance cost, refer to the Commission's impact assessment rather than vendor figures.
How much time do internal staff need for CRA work?
Internal time is usually concentrated in product owners, security engineers, developers and legal or compliance reviewers, and the load is highest during the first risk assessment and documentation cycle. Staff will need to explain product architecture, supply chain dependencies, update processes and how vulnerabilities currently reach engineering. Ask a partner to name the internal roles needed, the number of working sessions expected per product family and who signs off each deliverable. Your own staffing estimate should be based on your product count and existing security processes, so confirm it during scoping rather than assuming a figure in advance.
Can an implementation partner run the CRA process for us?
A partner can prepare systems, controls and evidence, but it cannot own your compliance or issue the conformity declaration. Your organization remains responsible for its products and must sign the EU declaration of conformity and affix CE marking where required. DeployOpen plans, implements, hardens, documents and supports self-hosted open-source platforms inside your own infrastructure, and it runs security testing for the products and systems in scope. Where a notified body is required for a product class, that body performs the independent assessment. Agree the division of roles in writing before work starts, so every deliverable has a clear owner.
Which CRA dates should we put on our compliance calendar?
Track the dates that change your obligations, starting with the reporting duty and the full application date. Add 11 June 2026 for the notified body chapter, 11 December 2026 as the Commission's milestone for sufficient notified bodies across Member States, and 30 October 2026 and 30 October 2027 as harmonized standards deadlines set in standardization request M/606. Also track 11 December 2027 for substantial modification and the support period changes, and 11 June 2028 for the validity of certain legacy type-examination certificates. Check each date against the official Commission implementation timeline, since it is updated as the regulation develops.
What should we confirm with official sources before signing a contract?
Confirm that the regulation text, the Commission guidance and the Commission FAQs you rely on are the current versions. Check the applicable dates in Article 71 on EUR-Lex, the product category descriptions in Implementing Regulation (EU) 2025/2392, and the status of harmonized standards in the Commission's FAQs. Ask your partner and auditors to cite the exact article, annex point or FAQ entry behind each deliverable. Confirm the current status of any standard or implementing act with the Commission and your national market surveillance authority before depending on it. Put these checks into the contract scope so that updates to the timeline are handled through a written change request.
How DeployOpen helps plan and prepare for CRA dates
DeployOpen helps organizations map the Cyber Resilience Act dates against their own product portfolio and infrastructure, then prepares the systems and evidence that the affected obligations need. We plan and implement self-hosted open-source platforms inside your own environment, and we do not issue audit reports, attestations or certifications.
How we scope
- We confirm which product families and release streams fall under the regulation's dates before work starts.
- Written scope lists the systems, teams, deliverables and milestones covered for each CRA date.
- Engagements are fixed-scope, with scope, deliverables and timelines agreed in writing before work begins.
How we build
- We implement and configure self-hosted open-source tooling for vulnerability intake, SBOM generation and release tracking.
- We set up documented workflows that record how reporting duties will be met from 11 September 2026.
- We test the configured workflows against the scope and document the results for your review.
How we hand over
- We deliver configuration records, runbooks and evidence templates that your staff can operate after handover.
- We document the date-by-date plan, showing which obligations apply to which products and when.
- Your organization owns its controls and decisions, and an independent assessor or notified body issues any formal outcome.
How we support
- Ongoing support, upgrades and continuous testing are available as a retainer after the fixed-scope work ends.
- We can revisit the timeline plan when the Commission publishes further implementing acts, guidance or standards.
- Ask us to confirm in writing how support covers changes to tooling, documentation and evidence as dates approach.
Sources and further reading
- Regulation (EU) 2024/2847, Article 71 (EUR-Lex) ↗
- Regulation (EU) 2024/2847, Article 69 (EUR-Lex) ↗
- Regulation (EU) 2024/2847, Article 70 (EUR-Lex) ↗
- Cyber Resilience Act implementation, Shaping Europe's digital future ↗
- ENISA: The CRA Single Reporting Platform is launched ↗
- Commission FAQs on the Cyber Resilience Act, version 1.4 ↗